Cable voltage drop on a solar job: the DC and AC check

A cable can pass its current rating and still be the wrong cable. Current rating keeps it cool. Voltage drop decides what reaches the inverter and the house.

Part of the series The electrical checks on every solar job.

The run that catches people out is the one that is not standard. The array is on the far gable, the inverter goes in the garage, and the cable goes round the outside of the house. Nobody measured the route, so nobody worked out the drop. With four inputs on the design sheet, the check is quick arithmetic.

Voltage drop costs energy every day, and it narrows the margins you designed for

Every metre of copper has resistance. Current through it loses voltage, and the lost voltage times the current is power turned into heat in the cable, on every sunny day for the life of the system. Three things make it more than a loss.

  • The DC side eats into the MPPT margin. The inverter sees the string voltage minus the drop. Drop grows with current, so it peaks on a bright, hot afternoon, when the string's voltage is already at its lowest. A string sized close to the MPPT minimum loses its margin in the cable. Start-up is different: the inverter wakes on open-circuit voltage with almost no current flowing, so the drop barely touches it.
  • The AC side is a voltage rise, not a drop. Whenever the inverter generates, current flows out to the consumer unit, so the inverter's terminals sit above the consumer unit's voltage by the amount the cable loses. Where the supply already runs high, a long, thin AC run pushes the inverter into its over-voltage trip on the best days of the year.
  • The same resistance slows the protection. A long run of small cable adds to the AC circuit's fault loop impedance, and the protective device needs a low enough impedance to disconnect in the time your wiring rules require. A cable that fails on drop is the first to check on disconnection time.

Four inputs: the length there and back, the current, the cable and its temperature

  1. Length, both ways. Measure the route the cable will take, not the distance on the plan. Current goes out on one conductor and back on the other, so a DC or single-phase AC run has twice its route length of copper in it.
  2. Current. On the DC side, the string's operating current, Imp, multiplied by the strings sharing that cable. On the AC side, the inverter's maximum AC output current from its datasheet, or its AC power divided by the supply voltage.
  3. Cable. Its conductor resistance in ohms per kilometre, from the cable maker's datasheet. Tinned, finely stranded solar cable has a different figure from twin and earth of the same size. Where your wiring rules publish a drop per amp per metre (mV/A/m), use it: it already counts both conductors, and it is given at the conductor's operating temperature, so do not apply the temperature correction below again.
  4. Temperature. The datasheet resistance is at 20 °C. Copper's resistance rises by about 0.4 % for every degree warmer, and DC cable on a roof in summer runs well above 20 °C.

The sum is Ohm's law, twice the length long

In words: the drop is twice the route length, times the current, times the resistance per metre. Divide by the circuit's voltage and multiply by 100 to compare it with the limit.

Vd = 2 × L × I × R and drop % = Vd ÷ V × 100, with L in metres, I in amps, R in ohms per metre, and V the string's Vmp on the DC side or the supply voltage on the AC side. The power lost in the cable is Vd × I. A three-phase run uses √3 in place of the 2, and V is then the line-to-line voltage. On domestic cable sizes, reactance is small enough to ignore.

Worked example: a 25 m DC route and a 15 m AC run

This example's own figures: twelve 440 W panels (Imp 12.80 A, Vmp 34.38 V) in two strings of six, one on each tracker of a 5 kW single-phase inverter. Each string has its own cable pair along a 25 m route, in 4 mm² solar cable at 5.09 Ω/km at 20 °C. The AC run to the consumer unit is 15 m of 4 mm² cable at 4.61 Ω/km, on a 230 V supply.

  1. DC, one string. String Vmp: 6 × 34.38 = 206.3 V. Copper in the loop: 2 × 25 = 50 m, at 0.00509 Ω/m that is 0.2545 Ω. Vd = 12.80 × 0.2545 = 3.26 V. Drop: 3.26 ÷ 206.3 × 100 = 1.58 %. Loss: 3.26 × 12.80 = 41.7 W per string at full output.
  2. DC, warm. At a conductor temperature of 60 °C, 40 degrees above the datasheet, resistance is about 16 % higher: 3.77 V, or 1.83 %.
  3. AC. Current: 5,000 ÷ 230 = 21.74 A. Copper in the loop: 2 × 15 = 30 m, at 0.00461 Ω/m that is 0.1383 Ω. Vd = 21.74 × 0.1383 = 3.01 V. Drop: 3.01 ÷ 230 × 100 = 1.31 %. At full output the inverter sits 3 V above the consumer unit.
  4. Together. The worst DC circuit plus the AC run: 1.58 + 1.31 = 2.89 % cold, 3.14 % with the warm DC figure.

Whether those numbers pass is not the formula's call. The permitted drop comes from your wiring rules. The inverter maker's installation manual can set its own figure for the DC input and the AC connection, so read it and use the tighter of the two.

When it fails, change the route, the cable or the string before you change the limit

  • Shorten the route. A straighter path or a different entry point costs nothing. Try it first.
  • Go up a size. In the example, 6 mm² solar cable at 3.39 Ω/km brings each DC string to 2.17 V, 1.05 %, and the loss to 27.8 W a string. The bigger cable costs once. The lost energy costs every year.
  • Lengthen the string. Twelve panels in one string run at 412.6 V on the same 12.80 A. The drop is still 3.26 V, but that is 0.79 % of the string voltage, and one cable pair loses 41.7 W instead of two. Run the string checks again first: how many panels can a string take covers them.
  • Move the inverter. Closer to the array shortens the DC run and lengthens the AC run. In the example a metre of DC costs 0.063 % and a metre of AC 0.087 %, so moving towards the array does not help this job. Work out both sides for each position.

Write the route length, cable, current and drop for each circuit on the design sheet, which can start as a paper sheet. A figure never written down is one nobody can defend when the inverter trips.

Installa checks the drop on the runs you draw

  • Stop working the drop out on a separate sheet. The DC and AC runs drawn on the design are checked in the validation results on the job's system design screen. This works the drop out on the same runs the quote prices.
  • Stop guessing the length. Each run uses the length set on it, else the run measured on the survey, else a typical length flagged as assumed. A length typed on the quote's cable line goes back on the run, so that the quote and the check never disagree.
  • Stop forgetting the isolator in the middle. A run through a DC isolator or junction box is added up as one circuit, and separate strings are never added together. This judges the circuit on its total drop.
  • Stop judging against a number in your head. Where the job's country has figures in Installa's rulebook, a drop over the recommended figure is a warning and over the maximum an error, and the worst DC circuit plus the AC run is judged against a system figure. Each cable is also checked for current against its rating. This keeps the limit with the job's country, not the designer's memory.
  • Stop sizing up by trial. A DC circuit that fails comes with a suggested cable size for its whole length, or, on a long run, a prompt to shorten the route or move the inverter. This puts the fix next to the fault.

Measure the route, double it, and compare the drop with your wiring rules and the inverter maker. See how electrical validation in Installa works, or use the string sizing calculator for the string voltages your DC sum starts from.