Nobody reads a handover pack on handover day. It gets read years later, when a light on the inverter turns red, or the house is sold and the buyer's solicitor asks for the certificates.
Part of the series Planning and running the install.
So write it for a customer on their own, with no installer on the drive. They need to prove what they own, understand what it is doing, know what to do when it stops and know who stands behind it. Group the pack under those four needs and they find what they want without ringing you.
The papers that prove the system is legal, safe and theirs
- The installation certificate. It is the proof the system was installed to the required standard, and the document a house sale asks for first.
- The electrical test certificate, with the results. The next electrician to touch the board needs the readings, not just the signature.
- The network operator's acceptance or notification. It shows the system is connected with permission.
- Any building, planning or landlord consent. A consent nobody can find is treated as a consent nobody got.
- The signed contract and the final scope. It settles what was sold, extras included.
- The design. The roof layout, the strings and the cable routes tell the next engineer what is under the panels without lifting one.
What normal looks like, so they do not ring you about a cloudy week
- A one-page summary of the system. The size, the address, the job reference and the commissioning date answer the first four questions any engineer will ask.
- The equipment fitted, with make, model and serial number. A warranty claim or a replacement part starts with the serial, and the customer cannot read it from the roof.
- The monitoring login. The app or website, the site ID and the email they sign in with, never the password, so they can check it themselves after a new router.
- How to read the inverter and the battery. What each light means, and why output drops in winter and stops at night, in plain words.
- The makers' datasheets and manuals. The engineer who comes in year eight needs the exact model's limits, not a guess from the label.
- What was there before. An older system kept or taken out is part of the property's history, and the next installer needs to know it exists.
When it stops: what they can safely do, and what they must leave alone
- How to switch the system off safely, step by step. Written for this job's kit, in the order this kit needs. Say plainly that the panels and the DC cables stay live in daylight whatever is switched off.
- Where every isolator is. A labelled photograph of each one beats a description of "the grey box in the loft".
- Three checks before they ring. Is the monitoring offline because the Wi-Fi changed, has an isolator been knocked off, is it simply dark or overcast.
- What not to touch. No cleaning from a ladder, no opening the inverter, no moving the battery. Say it plainly once.
- Photographs of the finished system. The labels and the cable runs in the loft show an engineer what is there before they arrive.
Who stands behind it, and the number to ring
- Each maker's warranty, with its length. Panels, inverter and battery carry different terms, and the customer will not remember which is which.
- The warranty registration for each unit. The reference and the date prove it was done, and a claim starts with them.
- Your workmanship warranty, and any guarantee that backs it. It tells the customer what you will put right at your cost, and what protects them if you are not there to do it.
- The reference for any export payment or tariff the system is registered with. The customer needs it to be paid, and a new owner needs it to transfer the payments.
- Who to ring, and what to have ready. Your phone number and email, the job reference, and a line saying the serial and a photo of the inverter screen will speed things up.
Every item above is only as good as what was written down on site. The serials, the test results and the monitoring login all have to be recorded before the van leaves, and what to record at commissioning is the list for that.
Send it in one piece, and make sure you can find it again in ten years
A pack that arrives in five emails is no pack at all. Run the same five steps on every job. The list above works printed and pinned up until it becomes habit.
- Build it from the job, not from memory. Gather it in the week of commissioning, while the crew still remember the job.
- Check it against the list before it goes. Anything not ready is named in the pack as "to follow", with the date it will arrive, so the customer is not left guessing.
- Send it all together, and ask the customer to confirm it arrived. The pack and its certificates and datasheets go in one send, not a trail of emails. Leave a printed copy of the shutdown steps by the inverter as well.
- Resend the whole pack when something changes. A late certificate goes into a rebuilt pack, not a separate email, so the customer always holds one current version.
- File the pack against the customer and the address. Ten years on, the caller can be a new owner who has never heard of you. Find the pack by the address and that call becomes a service visit or a battery quote. Your customers from ten years ago covers what to do with that installed base.
Installa builds the handover pack from the job for you
- Stop assembling the pack by hand. One click builds it as a PDF from what the job already holds: the summary, the design, the kit fitted with its serials, the certificates, the warranties, the monitoring login and who to call. Where the job's country has a pack defined, its sections follow that country's rules. This keeps the pack matched to where the system was fitted.
- Stop sending it with gaps you did not see. Anything not yet in the pack is listed on the screen with a link to the place that adds it. The customer's copy says which items are to follow, so nothing is quietly missing.
- Stop writing the shutdown steps on every job. Write your shutdown procedure and monitoring guide once, in your own words, with fields for the inverter, the battery and the monitoring login. Each pack fills them in for the kit fitted, so the steps always name the right equipment.
- Stop attaching datasheets job by job. Upload a maker's datasheet once on the product, and every pack that product is fitted on carries it. This keeps the customer's copy matched to their roof.
- Stop wondering whether it arrived. Sending the handover is one click that emails the customer in your brand, and it warns you first if documents were added after the pack was built. The customer opens the pack in their portal and confirms they have received it, and the date goes on the job's history.
- Stop searching old drives. Every pack built stays on the job, beside its documents filed by category. The Documents page filters by category and finds a file by the customer it belongs to, so the pack from years ago is one search away.
Build the pack from the job, check it, send it once, ask for confirmation and file it where the address will find it. That is the whole routine. See how scheduling and the job file in Installa work.