What to record at commissioning, so nothing is chased afterwards

The certificate with the wrong serial was not written in the office. It was written on the drive, on the back of a delivery note, at the end of a long day.

Part of the series Planning and running the install.

Everything the office chases later is a blank left on the day

The electrician finishes at six, writes the serials on whatever paper is in the van and heads home. A week later the office needs them for the certificate and the warranties, and nobody can read the third digit. Somebody drives back out to photograph a label.

Every item below is something the office needs within days of commissioning and cannot find out from a desk. Record each one on site, against the job, before the van leaves: the kit fitted, every serial, the test results, the settings and the photographs. Write "not fitted" or "not known" in words when that is the answer, because a blank tells the office nothing. A printed sheet in the van is enough to start.

The equipment: what is on the roof, not what was sold

The design says what was meant to go up. These lines say what did.

  • Each item on the design marked fitted or not fitted. The certificate and the warranty describe the system that exists, not the quote.
  • Any swap, with the model that went in instead. A different inverter changes the datasheet, the warranty and the settings the network operator expects.
  • The serial number of every panel, inverter, battery, optimiser and meter. The certificate, the warranty registration and every fault call later start from it.
  • A clear photograph of every rating label. When a serial is queried, the photograph settles it without a visit.
  • Where the inverter, battery and isolators are. The next engineer finds them without ringing the customer to ask.

The tests and settings: the numbers nobody can go back for

A test result copied up a week later is a guess. These are written as they are taken.

  • Every test your installation certificate asks for, with its value. The certificate is filled in from this record, not from memory.
  • Each string's open-circuit voltage, short-circuit current, polarity and insulation resistance, and protective earth continuity where an earth is fitted. Recorded per string, they are the baseline every future fault is compared against.
  • The export limit the network operator granted, the value set on the inverter, and where the export-limiting CT or meter sits and which way it faces. The inverter must be set at or below the granted limit, and a CT fitted the wrong way round lets the system export more than it should.
  • The grid protection settings and the firmware version. A setting changed later by an update is only spotted if the original was written down.
  • The battery's mode and reserve level. The customer asking why the battery empties at night is answered from the record.
  • The monitoring connected and reporting, with the login email and the site reference. Monitoring that never connected is the second visit nobody pays for.
  • The commissioning date and who commissioned it. Every certificate, notification and registration deadline is counted from that day.

The photographs: answers to questions asked a year from now

Each photograph is filed against the job under a name, so it is found again without scrolling.

  • The roof before work started. A slipped tile reported next spring is answered with a dated picture.
  • The fixings and flashing before the panels covered them. Nobody sees them again without lifting the array.
  • The cable route, inside and out. The next trade knows where the cable runs before they drill.
  • The consumer unit or switchboard, isolators and warning labels, finished. These are the photographs an assessor and the next electrician ask for.
  • The inverter and battery in place, with the space around them. The siting and clearances are shown, not described.
  • The finished array and the inverter display on the day. The system worked when you left, and the photograph proves it.

What the customer is told, and what the office starts that day

Commissioning ends with the customer, and the paperwork starts the same afternoon. What the customer receives afterwards is set out in what goes in a handover pack.

  • The customer shown the monitoring working on their own phone. A customer who can read it does not ring to ask whether it is working.
  • How to isolate the system, and what the inverter lights mean. The safety question is answered before it is a worry.
  • What paperwork arrives, and when. The customer waits for a date instead of chasing for "any update".
  • Any snag, with an owner and a date. A snag written down gets closed, and one only mentioned gets forgotten.
  • Any certification scheme's certificate, the network operator's notification and each manufacturer's warranty registration, with a due date each. Each clock runs from the commissioning date, so each needs a name against it that day.

The sheet gets skipped on the late finish, which is when it matters

Two things keep it filled in. First, the job is not called commissioned until every line is filled or marked "not fitted" or "not known", and the office checks it before the electrician leaves the drive. Second, one named person in the office owns the deadlines that start that day, with a stand-in for holidays. Before commissioning comes the date itself: see holding the install date.

Installa keeps the commissioning record for you

  • Stop copying serials off a sheet in the van. The commissioning screen lists what the job's design says was going in. Each item is marked fitted or not fitted, a swapped model is changed in place, and the serials are typed or keyed in with a barcode scanner beside a photograph of the label. This keeps the record true to the system on the roof.
  • Stop finding the wrong serial on the certificate. Installa flags a serial that does not fit the product's format, a row with fewer serials than units, and a serial already recorded on another job. The mistake is caught on the day, not when the certificate comes back.
  • Stop commissioning with blanks. "Mark commissioned" waits until the checklist is complete: serials, monitoring reporting, the export limit where the grid process asks for one, the tests and photographs the job's market asks for. Commission anyway and Installa writes what was still open to the job's history, so the gap stays visible.
  • Stop counting the days by hand. The commissioning date sets the due date on every job-file item that runs from it. This puts anything overdue or due within a fortnight on the dashboard's needs-attention list.
  • Stop asking which warranties are registered. Each unit records who it was registered with, the reference and the date, and the checklist names the units still to do. This shows the office the gap without opening the manufacturers' portals.

Every item fitted, every serial, every test and every photograph recorded on the day, and the deadlines started that afternoon. That is the whole routine, and it is what the commissioning screen and the job file are for. See how scheduling in Installa carries a job from the booked date to the handover.