Did that job make money? Knowing the margin on every solar install

The quote says what a job should make. Only the job can tell you what it did make, and only if somebody writes it down while it runs.

Part of the series Running a solar installation business by the numbers.

The job that looked fine on paper

A job is quoted at two days on the roof. The scaffold hire runs on an extra week. The quoted inverter is out of stock, so a dearer one goes in. A week after handover, an electrician goes back to pair the monitoring. Everyone was busy, the customer paid the quoted price, and the owner still believes the job made its quoted margin.

The quoted margin is a plan. The margin you made only exists once the job's actual costs are set against the quoted ones. Until then, the next quote is priced on a number nobody has checked.

The quote was costed. The job was not. Four places the difference hides.

  1. Labour was never a number of days. The quote carried labour as one lump, or buried it in the price of the panels. When the job took an extra day, nobody could say whether that day was in the price.
  2. Nobody owned recording the extra time. The second visit and the afternoon on a stubborn cable route were known to the crew. Nobody had been asked to write them against the job.
  3. The changes lived in a phone call and an invoice. The kit swap was agreed with the wholesaler on the phone. The scaffold extension arrived as an invoice weeks later and went to the accounts pile, never matched to the job it belonged to.
  4. Nobody looked. The job closed, the next one started, and there was no moment when the quote and the actuals were put side by side. So the same loss repeats on the next roof like it.

Cost the job twice on the same lines: once to win it, once to close it

This is the routine. It needs a cost sheet per job, the quote beside it, and ten minutes at the end. The first jobs can be done on paper.

1. Quote with a cost on every line, and labour in days

Every kit line on the quote carries two figures: what you charge and what it costs you. Labour goes on as crew days, so the quote says how many days the price buys. Its cost is the days times the full cost of a crew day, not wages alone, and the owner's own days on the roof are costed too. Write that labour cost once, under labour on the job sheet, and leave the labour line itself without a cost, so labour is never counted twice. Scaffold goes on as its own line with its hire period. What a solar quote should contain sets out the price line by line.

2. Open the cost sheet the day the job is won

Use the quote's headings: materials, labour, scaffold and subcontractors, everything else. Fill the quoted column, leave the actual column empty, and put one name at the top: the person who closes it.

3. Record the actuals as the job runs, not after

Each cost has one person who writes it down on the day.

  • The crew lead writes each day on site and each return visit, with who went and for how long, before leaving the job.
  • The office writes each supplier and scaffold invoice against the job as it arrives, and the date the scaffold came down.
  • Whoever agrees a change writes it: the substituted inverter and its cost, the extra length of cable, the extra week of hire.

4. Close every job with a ten-minute review

When the last cost for the job is in, the sheet's owner and the crew lead sit down with it. Go line by line: quoted, actual, the difference, and one line saying why. Then the job's figures: what it sold for before tax, less the actual costs, is the job's gross profit. The van, insurance, the office and the owner's time all come out of it, so the margin you aim for has to cover them. The gross profit divided by what it sold for is the margin. A job is not finished until its sheet is closed, and a sheet with a blank line is not closed.

5. Once a month, read the jobs that lost money

List the month's closed jobs by margin, lowest first. Mark every job that lost money or came in under the margin you set yourself. Read their reasons and find the one that repeats: scaffold hire running over, a second visit for the monitoring, extra days on one roof type. Then change one thing at its source: the day estimate, the scaffold line on the quote template, a question on the survey sheet. Write the change down with a name and a date, and check it at next month's review.

The cost sheet is the first thing dropped in a busy month. Two habits keep it.

Tie the closing review to a step the firm already takes. If the job cannot be marked complete until its sheet is closed, the sheet gets closed. Give each job's sheet a named owner with a stand-in, so a holiday does not leave a month of jobs uncosted.

Then treat a blank as unknown, never as nothing. A job with no costs recorded is not a job with a perfect margin. It is a job nobody has costed, and it stays out of the monthly figures and on a list until somebody does.

Installa sets every job's costs against its quote for you

  • Stop copying the quote onto a cost sheet. A quote line from your price list keeps what the product cost on the day it was added. On an accepted quote, "Take it from the quote" fills the job's revenue before tax, and fills material cost by adding up the cost of every charged line. It does so only when every charged line has a cost, so a part sum never passes for the whole. Keep labour lines on the quote without a product cost and enter crew labour on the cost sheet as hours times rate, so labour is counted once.
  • Stop keeping the actuals in a spreadsheet. Every job has a cost sheet: materials, labour hours and rate, subcontractors, other costs and notes, set against what the job sold for. A figure you typed is never replaced from the quote without asking you first.
  • Stop wondering when the figures moved. Each save names the figures that changed on the job's history. This shows at the closing review which costs were added late.
  • Stop reading a blank as a profit. A job with no costs shows no margin, only that its costs are missing. The profitability report counts it as not costed yet and keeps it out of the totals.
  • Stop sorting the month by hand. The profitability report lists each commissioned job's cost, profit and margin, sorts by lowest margin, splits the costs by type and shows margin month by month. This is the monthly review's list.
  • Stop holding the line in your head. Type your own margin target in the company settings and every costed job below it is flagged, with a filter to show only those. Until you set one, nothing is flagged.

Cost the job on the quote's lines, record what it really cost as it runs, and close it with ten minutes of quoted against actual. That is the whole routine, and it is what the reports in Installa are built to run.